10 Kilovolt LLC has been engaged in this type of activity for several years now, so you can safely contact us for help. Below is a table showing prices for all types of services provided. Our connection prices:
Price list for electricity connection | |||
---|---|---|---|
№ | Job title | Unit change | Price (RUB) |
1 | Turnkey electricity connection for individuals. persons (excluding materials) | pcs. | 60000 |
2 | Materials and their acquisition (standard 15 kW) | pcs. | 20000 | 3 | Documents and work over 15 kW for individuals. and legal persons (negotiable) | pcs. | from 60000 |
By stages | 4 | Conclusion of an agreement for technological connection and obtaining technical specifications (enhanced control of the application) | pcs. | 10000 | 5 | Execution of specifications (installation work) | pcs. | 25000 | 6 | All approvals for the construction of the electrical network and delivery to the electrical network inspector/energy supervision, power supply agreement, subscriber book, personal account | pcs. | 30000 | 7 | Simplified electrical diagram (single-line, without approvals) | pcs. | 3000 |
Connection of consumer electrical installations to the electrical network is carried out only on the basis of an approval certificate for the production of this connection. You can obtain permission to connect both the entire electrical installation and one of its components- everything will depend on the terms of the accession agreement.
Electrical installations, regardless of whether they are new, reconstructed or modernized, must comply with the requirements of regulations, as well as project documentation. In addition, they must have all the necessary documentation and be equipped with means of protection against electric shock.
The permit, which allows work to connect an electrical installation, is issued by the same organization that issued the technical specifications for connecting electricity.
For electrical installations that use foreign-made equipment that is subject to certification, such a certificate is required. This certificate must meet the requirements of the current regulations. Russian Federation standards.
In order to obtain an approval certificate for connecting an electrical installation to the network, the customer must contact the organization in charge of the electrical network in writing. Application for electricity connection must also contain:
- Technical conditions for connecting electricity and a certificate from the organization that issued them and carried out the connection.
- Project documentation, which is approved accordingly.
- Single-line diagram of electrical installation connection.
- An act that demarcates balance sheet affiliation And operational responsibility sides
- Information about which electricity metering devices are installed, and if differentiated metering devices are available, a protocol for their parameterization.
- The acceptance certificate, which must be signed by the construction, installation and commissioning organizations.
- A protocol that will confirm the knowledge test and an order to appoint a person responsible for electrical equipment (or an agreement for servicing the electrical installation of organizations that have the right to perform such work).
- List of persons who, on behalf of the customer, have the right to submit applications for disconnecting and connecting electrical installations.
- Executive plans and work certificates.
Video: technical conditions for connecting electricity
Gasket types:
Technical conditions (TS) for connecting electricity is a document that establishes a list technical requirements, which must be completed in order to connect to electricity networks, increase the power consumption limit, etc.
Obtaining technical conditions is the first stage in such a long procedure as joining electrical networks. Without this document, it is impossible to either develop or connect the electrical supply to a residential or commercial property. Its registration must precede the design of networks and the creation of new power supply schemes, and all the requirements specified in the document must clearly comply with interstate and state standards. Obviously, it will be difficult to do without the support of a specialist. Firm Starling and Co. LLC is always ready to help.
The cost of obtaining technical specifications for electricity supply
The amount it will cost to obtain technical specifications through us depends to a large extent on the power of the connected network, and only secondarily on the nature of the applicant (cheaper for individuals). You can see our tariffs in the table below. They are approximate - the exact figure is always determined individually, taking into account the specifics of the request and discounts and special offers valid at the time of application.
How to obtain specifications for connecting electricity
You can obtain technical specifications in Moscow and the Moscow region on your own, but this document is one of the most standardized, and there should be no errors in its execution. Otherwise, there may be electrical problems in the future. Therefore, think carefully about whether you want to understand all the nuances of this procedure? Are you ready to spend time on self collection documents, filling out an application, contacting JSC “MOESK”?
You can and should entrust us with obtaining technical specifications for connecting the power supply. Representing the interests of clients, we act according to a long-established scheme, so the entire process takes a minimum of time. You will only be required to provide the following information:
Electricity sources,
Attachment points
Amount of power consumption,
Calculated current values,
Limit of responsibility
All requirements of your electricity supplier (before receiving the document),
Test calculations of cable and additional equipment (switches, transformers, meters, fuses, etc.).
We will also need:
The purpose of the object or premises,
Official location (for CJSC or LLC legal address),
Time to put the facility into operation,
Calculation of predicted power ( required quantity kW and power supply reliability category).
Obtaining technical specifications for power supply through us takes place in several stages:
Providing a description of the object, collecting documents. Don’t think that there are insignificant details here; don’t limit yourself to general phrases. The more detailed your description is, the better.
Document development. The basis for it is GOST 2.114-95 and GOST R. 51740. In the first, general rules for design documentation, and in the second - private design requirements. It will be difficult for non-specialists to understand.
Coordination and approval. At this stage, coordination takes place both with the inspection authorities and with the customer.
By entrusting this work to us, you will save the most important thing in life - time, which is much more valuable than the money spent. Getting technical specifications with us is profitable!
Application and list of documents for obtaining technical specifications
LLC "Firm Starling and K" takes on all the concerns once our clients achieve such a goal as obtaining specifications for power supply. We provide comprehensive assistance and support at all stages of work, starting with contacting us and filling out an application. By the way, a sample application form is available on our website for your reference.
In addition, you will also need the following documents:
location plan of all power receiving devices to be connected;
documents confirming the location of the property of JSC "MOESK" with the shortest distances from the territorial border;
single-line diagram of the applicant’s electrical networks with a voltage class of 35 kW or more that need to be connected. The possibility of redundancy and load generation is indicated;
title documentation for a given object;
constituent documents;
documentation confirming the applicant's credentials.
Please note that the composition of the documents may vary depending on whether the legal or an individual is the subject, as well as the power of the connected network. The above list of documents for obtaining technical conditions for connection is approximate. We can determine the exact list when you contact us.
Technical specifications for power supply must be obtained when connecting objects to power grids. Specifications are also required when the level of energy consumption changes. Stroy-Proekt LLC offers qualified assistance in resolving this issue.
Obtaining technical conditions for connecting to engineering networks necessary to determine the category of reliability of power supply, power of energy consumers, voltage indicators and connection point. Specifications in Moscow are provided only by permitting and inspection organizations:
- Rostechnadzor;
- OJSC Mosenergosbyt;
- JSC "MOESK".
Specialists of the Stroy-Proekt company are ready to prepare papers for expert analysis as quickly and efficiently as possible. Before submitting documents, they are edited.
Prices for obtaining technical specifications
The procedure for obtaining technical specifications for power supply
The enterprise operating electrical networks determines and provides technical specifications within 14 working days from the date of receipt of the request. In case of refusal, the decision must be motivated. To check the validity of a negative answer, the applicant applies to the authorized federal authority for technological supervision.
The cost of obtaining technical specifications is determined network organization. When connecting buildings put into operation for the first time to the electrical grid, the volume and principle of distribution of work tasks between the parties signing the contract are determined. Also, obtaining specifications is necessary when improving the electrical installations used.
Required documents
The owner of the property connected to the electrical grid must submit an application. It must indicate:
- full name, functional purpose and the address of the building or premises;
- previously installed power and one-time load;
- element of the electrical network to which connection is planned;
- already allocated and requested additional capacities and their target distribution between the main consumer and subsubscribers;
- names of the developer and investor;
- start date construction work and putting the facility into operation;
- requirements for the reliability of power supply to receiving devices;
- nature of the load and special conditions.
The following is provided as an attachment to the application for technical specifications:
- situational plan land plot or premises on a scale of 1:2000;
- copy of passport;
- a certificate from the energy sales company confirming that there is no debt;
- a copy of an extract from the technical passport of the BTI;
- a copy of the certificate confirming ownership;
- written agreement additional capacity with the owner of the electrical networks.